Understanding Line Target Calculation
This formula helps manufacturers determine how many products can be produced within a given time based on workforce, efficiency, and standard production time.
Parameters Explained:
- Total Manpower (MP): The total number of workers (helpers + operators) involved in production.
- Working Hours (WH): The total number of hours the production line operates.
- Standard Minute Value (SMV): The time required to manufacture one unit in minutes.
- Efficiency: The effectiveness of labor and time utilization (expressed in percentage).
Real-Life Applications:
- Manufacturing Industry: Helps in setting production targets and workforce management.
- Quality Control: Ensures that the expected number of units is achieved within given resources.
- Labor Productivity: Optimizes workforce allocation for better performance.
Conclusion:
A well-calculated line target leads to better efficiency, cost savings, and smooth production flow.